top of page
WWES Wetlands.HEIC

COST

We currently estimate the total cost for the project to be $21.6 million. A final budget cost for the project will be completed during Schematic Design and presented to the City Council for approval in the Fall of 2021.

​

ELIGIBLE VS. INELIGIBLE COSTS​

The MSBA reimbursement is 54.79% for any ELIGIBLE expenses.

​

There are a number of things in the project that are not eligible for reimbursement or exceed the maximum eligibility caps. For example, site costs over 8% are not eligible.

​

We are estimating ~ 40% realized reimbursement after eligible/ineligible costs are calculated.

MSBA.jpg
DW Logo - Color_Combined Logo.png
DRA-Logo-New.jpg

© 2024  Tri-County Regional Vocational Technical School District